Estimated Value
Not disclosed
Deadline
Not specified
Contract Period
Not specified
Procurement Method
selective
Extracted from the notice; check the official documents.
Construction of a 50m highway stabilisation retaining wall along the A377. Approx. 23.5m of piled wall with timber parapet and approx. 26.5m of mass concrete wall with masonry parapet and associated highway resurfacing (estimated 970m). Start on site 14 September 2026
BRIDGE CIVIL ENGINEERING LIMITEDSME
Value not stated · Awarded 17 Aug 2026 · Contract ends 12 Mar 2027 · Award notice ↗